RACI Matrix

– Project PASS PMP


Purpose

This matrix defines who does what across major deliverables and management processes.
The RACI model clarifies the distinction between:

  • R – Responsible: Performs the task or activity
  • A – Accountable: Owns the outcome and approves completion
  • C – Consulted: Provides input or subject matter expertise
  • I – Informed: Receives updates or notifications

This helps prevent confusion, overlapping roles, and missed accountability checkpoints.


Project Roles

RoleDescription
SponsorApproves deliverables, validates decisions, controls funding
Project ManagerOversees scheduling, coordination, and delivery
Content DeveloperProduces lessons, case studies, and glossary content
ReviewerEnsures content accuracy and alignment with ECO
Technical LeadManages publishing systems, GitHub, and Quartz/Obsidian pipelines
ContributorSupports documentation or media updates
StakeholderReceives updates, feedback, and review access

RACI Matrix Table

| Deliverable / Process | Sponsor | Project Manager | Content Developer | Reviewer | Technical Lead | Contributor | Stakeholder | |-----------------------|----------|-----------------|------------------|-----------|----------------|--------------| | Scope Management Plan | A | R | C | C | I | I | I | | Schedule Management Plan | A | R | C | C | I | I | I | | Cost Management Plan | A | R | C | I | I | I | I | | Resource Management Plan | A | R | C | I | I | I | I | | RACI Matrix | I | A | C | C | I | I | I | | Content Development (Lessons) | I | A | R | C | I | R | I | | Glossary and Templates | I | A | R | C | R | R | I | | Case Study Lab | I | A | R | C | I | R | I | | Risk Register Updates | A | R | C | I | I | I | I | | Performance Reporting | A | R | C | C | R | I | I | | Publishing to GitHub Pages | I | C | C | I | A | R | I |


Interpretation Guidance

  • Accountability Rule: Only one β€œA” per task
  • Responsibility Rule: Multiple β€œR”s may exist but must coordinate with the β€œA”
  • Consulted: Brings expertise β€” they are engaged before decisions
  • Informed: Receives updates β€” they are not decision-makers


Review and Approval

NameRoleSignatureDate
SponsorProject Authority
Project ManagerResource Owner

πŸ“Œ Use this document as a teaching reference and a living accountability tracker. It ensures that every contributor knows exactly where they fit in the project’s responsibility structure.