Resource Calendars

– Project PASS PMP


Purpose

This document outlines when team members and key resources are available during the project.
It ensures:

  • Schedule feasibility
  • Workload balancing
  • Alignment with milestone delivery
  • Transparency around constraints

This file supports:


Resource Availability by Week

ResourceRoleWeek 1Week 2Week 3Week 4Notes
SponsorSponsorβœ…βœ…πŸ”²πŸ”²Hands-off after planning
PMProject Managerβœ…βœ…βœ…βœ…Full availability
Content DevContributorπŸ”²βœ…βœ…βœ…Starts post-baseline
ReviewerQA/SMEπŸ”²πŸ”²βœ…βœ…Reviews lessons + glossary
Case WriterContributorπŸ”²πŸ”²πŸ”²βœ…Single deliverable
Tech LeadPublishingπŸ”²πŸ”²βœ…βœ…Quartz setup + deploy

Sprint-Based View (Alternative Format)

If managing work in sprints, structure availability like this:

SprintResourceCommitted HoursAvailability Issues
Sprint 1PM, Sponsor10 hrs / 10 hrsNone
Sprint 2Content Dev15 hrsReview delay possible
Sprint 3Reviewer, Tech Lead8 hrs, 6 hrsGlossary revision cycle
Sprint 4All roles100%Final QA and publish

Capacity Conflict Resolution

If a resource is overbooked or unavailable:

  • The PM will reallocate or defer work
  • The Training Plan may be used to onboard backups
  • Notes will be added to the Team Charter


Approval

NameRoleSignatureDate
PMScheduler
SponsorApprover

πŸ“Œ Use this calendar to validate who is available, when they’re available, and how their effort fits into the delivery plan. All estimates and schedules rely on this file for reality-checking availability.