Schedule Management Plan
Project: Project PASS PMP
Folder: /20-schedule-management/
1. Purpose
This plan defines how the schedule for Project PASS PMP will be:
- Developed
- Sequenced
- Monitored
- Controlled
- Reported
It supports timely delivery and transparency throughout the project lifecycle.
2. Schedule Planning Approach
Scheduling will follow a rolling wave approach:
- High-level milestones established early
- Detailed task planning done progressively
- Dependencies and durations recorded in the Detailed Project Schedule
3. Roles and Responsibilities
| Role | Responsibility |
|---|---|
| Sponsor | Approves milestones and baselines |
| Project Manager | Owns the schedule; tracks updates and reports performance |
| Content Developers | Update task status, provide time estimates |
| Contributors | Follow task dates, raise delays early |
4. Tools and Formats
- Tool: Obsidian for schedule planning in Markdown
- Format: Markdown tables and performance logs
- Backup Format: CSV export (if needed for conversion)
5. Schedule Components
This project uses the following schedule-related artifacts:
| Document | Description |
|---|---|
| 02-detailed-project-schedule | Full list of scheduled tasks and durations |
| 03-milestone-list | Key delivery checkpoints |
| 04-schedule-baseline | Locked schedule baseline for performance tracking |
| 05-schedule-change-log.md | Approved changes to the baseline |
| 06-schedule-performance-report.md | SPI, variance, and actual vs. planned metrics |
6. Schedule Baseline
The Schedule Baseline is the approved version of the full project schedule.
It will be used to measure performance and cannot be changed without an approved Change Request.
7. Schedule Control and Change Management
All changes to the schedule baseline must be:
- Logged in the Schedule Change Log
- Reviewed for impact on scope and cost
- Approved by the Sponsor
8. Performance Reporting
Performance will be monitored using:
- Schedule Performance Index (SPI)
- Planned vs. Actual Completion
- Milestone tracking
See: Schedule Performance Report
9. Assumptions and Constraints
Assumptions
- Milestone sequence follows Simplilearn pacing
- Sponsor reviews schedule weekly
- GitHub commits reflect actual work status
Constraints
- Weekly publishing deadlines
- Time-limited review windows
- No full-time team members; contributors are part-time
10. Approval
| Name | Role | Signature | Date |
|---|---|---|---|
| Sponsor | Project Owner | ||
| PM | Schedule Manager |
This plan defines the rules and artifacts for scheduling across the full project lifecycle. All contributors should understand how scheduling affects deliverables, dependencies, and final exam preparation timelines.