Detailed Project Schedule

Project: Project PASS PMP
Folder: /20-schedule-management/

This document outlines the full schedule of activities required to complete the project, organized by workstream, with durations, dependencies, and status for each task.

📌 This schedule is referenced by the Schedule Baseline and feeds into the Schedule Performance Report.


Workstreams and Tasks

WBS IDTask NameStart DateDuration (Days)DependencyOwnerStatus
1.1.1Define lesson structure (ECO-based)Oct 142Sponsor✅ Complete
1.1.2Create Schedule Management PlanOct 1621.1.1PM Lead✅ Complete
1.1.3Draft detailed project scheduleOct 1811.1.2PM Lead✅ Complete
1.1.4Write milestone listOct 1911.1.3PM Lead✅ Complete
1.1.5Set schedule baselineOct 2011.1.4Sponsor🔲 Pending
1.2.1Write lessons (100 series)Oct 2151.1.5Content Dev🔄 In Progress
1.2.2Write glossary draftOct 2821.2.1Content Dev🔲 Not Started
1.2.3Develop case study 1 (Predictive)Oct 3021.2.2Case Writer🔲 Not Started
1.3.1Draft Schedule Change LogNov 0111.2.3PM Lead🔲 Not Started
1.3.2Build first performance reportNov 0211.3.1PM Lead🔲 Not Started
1.4.1Publish full schedule to GH PagesNov 0311.3.2Tech Lead🔲 Not Started

Legend

StatusMeaning
✅ CompleteTask finished and reviewed
🔄 In ProgressWork has started
🔲 Not StartedScheduled but not started

See Also


This file will evolve until the baseline is locked. Once locked, only changes via Change Request may apply.