Schedule Baseline – Project PASS PMP

Folder: /20-schedule-management/
Bloom’s Level: 2 – Understanding (Interpret, Apply, Describe)


📎 Purpose

The Schedule Baseline is the officially approved version of the full project schedule.
It represents the time-phased plan against which progress will be tracked.

Once approved, this document is locked and can only be modified through the formal change control process.


Baseline Summary

MetricValue
Baseline Approved DateOct 20, 2025
Total Planned Duration30 days
Number of Tasks10
Number of Milestones8
Review CadenceBi-weekly
Responsible ApproverSponsor

Baseline Schedule Snapshot

WBS IDTaskPlanned StartPlanned FinishDuration (Days)Notes
1.1.1Lesson structure finalizedOct 14Oct 152Complete
1.1.2Schedule Plan approvedOct 16Oct 172Complete
1.1.3Detailed schedule draftedOct 18Oct 181Complete
1.1.4Milestone list completeOct 19Oct 191Complete
1.1.5Baseline signed offOct 20Oct 201Sponsor approval required
1.2.1Lesson writing (100 series)Oct 21Oct 265Active development
1.2.2Glossary draftOct 28Oct 292Links to ECO
1.2.3Case Study 1Oct 30Oct 312Predictive example
1.3.1Performance report issuedNov 2Nov 21Includes SPI & variance
1.3.2Public site releaseNov 5Nov 51Major milestone

How the Baseline Is Used

This document is referenced by:


Governance Notes

  • Versioning: Each baseline version is tracked in YAML
  • Change Policy: Any adjustments must go through the Schedule Change Log
  • Audit Requirements: Keep this document in sync with all upstream schedule changes

Baseline Approval

NameRoleSignatureDate
SponsorApprover[Pending]
PMOwner[Pending]

This baseline is locked for control and performance measurement. All actual progress will be compared to this schedule using SPI, percent complete, and variance metrics.