Schedule Performance Report – Project PASS PMP

Folder: /20-schedule-management/
Bloom’s Level: 2 – Understanding (Interpret, Summarize, Explain)


πŸ“Ž Purpose

This document summarizes the current schedule health of Project PASS PMP.
It tracks progress against the Schedule Baseline using core metrics from Earned Value Management (EVM).

Metrics include:

  • Planned % Complete
  • Actual % Complete
  • Schedule Performance Index (SPI)
  • Variance from Schedule
  • Completion Commentary

Reporting Period

Report DateFrom DateTo Date
Oct 13, 2025Oct 1, 2025Oct 13, 2025

πŸ“ Schedule Performance Metrics

MetricDescriptionValueNotes
Planned % Complete% of tasks scheduled to be completed by report date40%Based on 4/10 tasks
Actual % Complete% of tasks actually completed30%3/10 tasks completed
Schedule Performance Index (SPI)EV Γ· PV0.75Behind schedule
Schedule Variance (SV)EV βˆ’ PV (expressed as %)–10%Indicates slippage
Tasks at RiskTasks slipping or blocked2Glossary draft, Case Study 1

πŸ“Œ SPI = Earned Value (EV) Γ· Planned Value (PV)
SPI < 1.0 = Behind schedule
SPI > 1.0 = Ahead of schedule


Summary Commentary

As of this reporting period:

  • Content work began on time, but glossary drafting and case study prep are behind.
  • Contributors flagged dependency delays on glossary completion.
  • Milestone MS-04 (β€œGlossary Skeleton Published”) is at risk of slipping 2 days.
  • Recovery plan in place: consolidate glossary using automated template links.

πŸ“Ž Key References


Future reports will be submitted bi-weekly until project closeout.
Metrics will be updated based on actual task progress logged in GitHub and Obsidian publishing status.