Navigation Section
Schedule Performance Report β Project PASS PMP
Folder: /20-schedule-management/
Bloomβs Level: 2 β Understanding (Interpret, Summarize, Explain)
π Purpose
This document summarizes the current schedule health of Project PASS PMP.
It tracks progress against the Schedule Baseline using core metrics from Earned Value Management (EVM).
Metrics include:
- Planned % Complete
- Actual % Complete
- Schedule Performance Index (SPI)
- Variance from Schedule
- Completion Commentary
Reporting Period
| Report Date | From Date | To Date |
|---|---|---|
| Oct 13, 2025 | Oct 1, 2025 | Oct 13, 2025 |
π Schedule Performance Metrics
| Metric | Description | Value | Notes |
|---|---|---|---|
| Planned % Complete | % of tasks scheduled to be completed by report date | 40% | Based on 4/10 tasks |
| Actual % Complete | % of tasks actually completed | 30% | 3/10 tasks completed |
| Schedule Performance Index (SPI) | EV Γ· PV | 0.75 | Behind schedule |
| Schedule Variance (SV) | EV β PV (expressed as %) | β10% | Indicates slippage |
| Tasks at Risk | Tasks slipping or blocked | 2 | Glossary draft, Case Study 1 |
π SPI = Earned Value (EV) Γ· Planned Value (PV)
SPI < 1.0 = Behind schedule
SPI > 1.0 = Ahead of schedule
Summary Commentary
As of this reporting period:
- Content work began on time, but glossary drafting and case study prep are behind.
- Contributors flagged dependency delays on glossary completion.
- Milestone MS-04 (βGlossary Skeleton Publishedβ) is at risk of slipping 2 days.
- Recovery plan in place: consolidate glossary using automated template links.
π Key References
- π Schedule Baseline
- π Milestone List
- π Schedule Change Log
Future reports will be submitted bi-weekly until project closeout.
Metrics will be updated based on actual task progress logged in GitHub and Obsidian publishing status.