Cost Management Plan – Project PASS PMP

Folder: /30-cost-management/
Bloom’s Level: 2 – Understanding (Describe, Apply, Interpret)


1. Purpose

This plan defines how costs will be:

  • Estimated
  • Budgeted
  • Baseline-locked
  • Controlled
  • Reported

It ensures financial discipline, supports budget approval, and defines cost control processes throughout the project lifecycle.


2. Cost Estimation Approach

Cost estimates will be based on:

  • Bottom-up estimation of tasks in the Detailed Schedule
  • Historical benchmarks from past study builds
  • Expert judgment from sponsor and content creators

Cost estimates are documented in the Cost Estimates file.


3. Budgeting and Baseline

Once estimates are complete, they are aggregated and phased into the Cost Baseline.
This baseline is:

  • Time-phased
  • Approved by the sponsor
  • Locked unless a formal Change Request is submitted

4. Funding Requirements

Funding needs are documented in Funding Requirements.
This includes:

  • Contributor hours and stipends
  • Tech stack or hosting costs
  • Estimated cost buffers for delays or rework

5. Roles and Responsibilities

RoleResponsibility
SponsorApproves cost baseline and funding gates
Project ManagerMaintains cost baseline, tracks variance
ContributorsLog time spent, provide effort estimates
Finance Reviewer (optional)Validates major changes

6. Cost Control and Variance Management

Cost performance is measured using:

  • Cost Variance (CV) = EV βˆ’ AC
  • Cost Performance Index (CPI) = EV Γ· AC

Variances greater than Β±10% must be escalated and logged via the Change Request Template.


7. Assumptions and Constraints

Assumptions

  • No paid contractors involved unless sponsor-approved
  • Sponsor’s time is considered β€œno-cost” but tracked for realism
  • All contributors are part-time and self-paced

Constraints

  • Total hours capped at [insert value]
  • No third-party integrations or licensing beyond current toolset

8. Cost Reporting

Updates are included in the Schedule Performance Report, with summaries of:

  • CPI trends
  • Burn rate (effort vs. timeline)
  • Budget-at-completion

9. Approval

NameRoleSignatureDate
SponsorBudget Authority
PMCost Owner

πŸ“Œ This plan governs all cost-related activities in Project PASS PMP. No cost changes or increases to the baseline may be made without formal change control.


Back to the Top

Section Contents