Cost Performance Report โ€“ Project PASS PMP

Folder: /30-cost-management/
Bloomโ€™s Level: 2 โ€“ Understanding (Interpret, Summarize, Explain)


Purpose

This report summarizes the current cost health of Project PASS PMP.
It compares actual costs against the Cost Baseline and tracks variance using core Earned Value Management (EVM) metrics.


Reporting Period

Report DateFromTo
Oct 15, 2025Oct 1, 2025Oct 15, 2025

Cost Metrics

MetricDescriptionValueNotes
Planned Value (PV)Budgeted cost for work scheduled$5,000Based on baseline
Actual Cost (AC)Cost incurred for work completed$5,500Includes overages
Earned Value (EV)Budgeted cost for completed work$4,500Less completed than planned
Cost Performance Index (CPI)EV รท AC0.82Over budget
Cost Variance (CV)EV โˆ’ ACโ€“$1,000Behind plan
Estimate at Completion (EAC)Forecasted total cost$11,500Trend-based projection
Budget at Completion (BAC)Total approved budget$10,000From Cost Baseline

๐Ÿ“Œ CPI < 1.0 means the project is over budget.
CV < 0 indicates cost overrun.
EAC > BAC means final costs will exceed planned budget.


Summary Commentary

As of this report:

  • Several contributors logged more hours than expected for content development
  • Glossary and case study work required extra iterations
  • Contingency funds may be applied; reforecast needed
  • Team plans to reduce effort on styling and visual polish to recenter budget

References


๐Ÿ“Œ This report will be updated bi-weekly, aligned with milestone checkpoints.