Cost Performance Trend Chart – Project PASS PMP
Purpose
This chart tracks cost performance trends across multiple reporting periods, using Earned Value Management (EVM) metrics:
- Cost Performance Index (CPI)
- Cost Variance (CV)
- Estimate at Completion (EAC)
- Budget at Completion (BAC)
It provides an easy-to-read visual and numerical breakdown of project cost health over time.
Trend Table
| Report Date | EV ($) | AC ($) | PV ($) | CPI | CV ($) | EAC ($) | BAC ($) | Notes |
|---|---|---|---|---|---|---|---|---|
| Oct 13, 2025 | 4,500 | 5,500 | 5,000 | 0.82 | –1,000 | 11,500 | 10,000 | Over budget (early) |
| Oct 27, 2025 | 6,800 | 7,600 | 7,200 | 0.89 | –800 | 10,900 | 10,000 | Trend improving |
| Nov 10, 2025 | 9,500 | 9,900 | 9,000 | 0.96 | –400 | 10,300 | 10,000 | Nearly recovered |
Observations
- CPI is improving over time → team is regaining cost control
- EAC is trending down → total projected spend is stabilizing
- Variance is narrowing → most overages occurred early in development
Interpretation Guidance
| Metric | What It Tells You |
|---|---|
| CPI < 1.0 | Project is over budget |
| CPI > 1.0 | Project is under budget |
| CV < 0 | Over budget in absolute dollars |
| EAC > BAC | Final spend expected to exceed plan |
Tips for Learners
- Pair this chart with the Cost Performance Report to see how metrics are calculated
- Compare to the Schedule Performance Report to assess time-cost alignment
- Use the trend to justify decisions about buffer use, resource shifts, or scope adjustments