Funding Requirements – Project PASS PMP

Folder: /30-cost-management/
Bloom’s Level: 2 – Understanding (Identify, Categorize, Allocate)


Purpose

This file outlines when funding will be needed and released, whether in full, partial, or milestone-based increments.
It aligns with:


Funding Schedule

Milestone IDDescriptionRequired FundsRelease DateNotes
MS-02Schedule Baseline Set$0Oct 20Initial planning phase
MS-03First lessons published$480Oct 26Funding for writing team
MS-04Glossary published$240Oct 30Includes markup + ECO linking
MS-05Case Study complete$180Nov 2Final delivery for phase
MS-08Final report + site publish$120Nov 12Final wrap-up work

Total Funds Required

$1,020, aligned to the Cost Estimates and Cost Baseline


Governance and Constraints

  • Funding decisions approved by Sponsor
  • Adjustments must be reflected in the Cost Change Log
  • No early releases unless tied to Change Request

📌 This document helps track the timing and rationale for cost releases.