Cost Estimates – Project PASS PMP


Purpose

This document captures detailed cost estimates for all key tasks, deliverables, and work packages.
It feeds into the Cost Baseline and is referenced in the Cost Management Plan and Cost Performance Report.


Estimation Method

  • Technique: Bottom-up estimating
  • Basis: Contributor rates, estimated hours, effort class
  • Assumption: Sponsor time not billed; contributors are part-time volunteers

Estimate Table

WBS IDTaskEst. HoursRate/hr ($)Est. CostNotes
1.1.1Define lesson structure4 hrs$0$0Done by sponsor
1.2.1Draft lesson set (100 series)16 hrs$30$480Content creation
1.2.2Glossary research + markup8 hrs$30$240Includes linking
1.2.3Case study development6 hrs$30$180Predictive scenario
1.3.1Performance + cost reporting4 hrs$30$120Two cycles
Total Estimated Cost$1,020

Update Instructions

  • Update whenever scope changes or contributor estimates shift
  • Once baselined, match against Cost Performance Report